All Articles

Overview of collaboration status and situation with Russian in-kind

The HL-LHC Project is entering the series construction phase and therefore most of the collaboration agreements are now focused on the production of final elements that will have their destination in the LHC tunnel and in the set of operational spares.

WP1 Project Management

Update on the HL-LHC Project Status - Issue 3

As mentioned in the closing remarks of the 8th HL-LHC Annual Meeting held at CERN (18th October 2018), the project is experiencing a mix of success and difficulties while passing from design and industrialization into construction.

WP1 Project Management

Update on the Collaboration Partners and Contributions

The 7th HL-LHC Collaboration Board took place during the 7th HL-LHC Annual Meeting in November 2017, jointly organized by CIEMAT and CERN in Madrid, Spain. One of the focuses of the 7th HLCB meeting was a summary of the existing agreements for in-kind.

WP1 Project Management

Update on Civil Engineering Work for HL-LHC

The two civil-engineering contractors, MARTI for the Point 1 works and IMPLENIA for the Point 5 works, are fully mobilized. The excavations of the shafts at Points 1 and 5 were completed in February 2019 and December 2018, respectively.

WP17 Infrastructure, Logistics and Civil Engineering
WP17 Infrastructure, Logistics and Civil Engineering

Production Readiness reviews

Two production readiness reviews where conducted at CERN: one for the pressure vessels and one for the MgB2 cable production.

WP6A Cold Powering

D1 and D2 and HO corrector review

In December 2018, a review of the design of the D2 correctors and HO correctors took place in CERN. The committee supported the selected designs that showed to reach the required performance.

WP3 IR Magnets

DFX review and design modifications

On the 31st January 2019 (with a 2nd final session on the 12th February), a DFX Conceptual Design Review was held at CERN. The DFX is a key element of the cryogenic powering line for the new magnets of the LHC interaction region at IP1 and IP5.

WP15 Integration and (De-)Installation
WP15 Integration and (De-)Installation

Technical reviews of the HL-LHC Beam Dump System, the Collimation System and the Crab Cavity System

The CERN internal review of the HL-LHC Beam Dump System [BDS] took place on February 5th and was chaired by Volker Mertens. It was to a large extent triggered by two observations from the LHC beam operation towards the end of Run2

WP1 Project Management

Decision to delay the IT String test by one year and to limit the IT String test to one year operation

The HL-LHC magnets and cold powering systems are planned to be tested individually on dedicated test benches in the SM18 test facility at CERN or at the collaborators test facility (e.g. at Fermilab in the USA).

WP16 IT String and Commissioning
WP16 IT String and Commissioning

Update on the collimator developments: first picture of the TCLD from CINEL

One important upgrade for HL-LHC is the installation of new collimators, called TCLD, in the dispersion suppressors next to IR7 and IR2. The TCLDs are needed for proton and heavy-ion operation to intercept particles that differ from the main beam.

WP5 Collimation