  • Progress on the Civil Engineering preparation for P1 and  P5 of the LHC

    Progress on the Civil Engineering preparation for P1 and P5 of the LHC

    The key highlights of the Civil Engineering work include the completion of the preliminary design of the civil engineering works at Point 1 and Point 5 at the end of 2016 by the external Consultants. The Consultants also performed an independent cost estimate for the civil engineering work which falls within the project cost estimates…

  • TDR V0.1 and Baseline Change Documents

    TDR V0.1 and Baseline Change Documents

    Following the re-baselining exercise for the HL-LHC project in June 2016, the HL-LHC project implemented several scope changes (e.g. reduction of the Crab Cavity installation to only ½ of the initially planned system and suppression of the Q4 quadrupole upgrade) with respect to the PDR that was issued at the end of the EU funded…

  • Update on the Collaboration Partners and Contributions

    Update on the Collaboration Partners and Contributions

    The 6th HL-LHC Collaboration Board took place during the 6th HL-LHC Annual Meeting in November 2016, jointly organized by CEA and CERN in Paris, France. One of the focuses of the 6 th HLCB meeting was the launch of the new HL- LHC Memorandum of Understanding (MoU) for signature and the advertisement of opportunities for…