HO correctors

D1 and D2 and HO corrector review

In December 2018, a review of the design of the D2 correctors and HO correctors took place in CERN. The committee supported the selected designs that showed to reach the required performance.

WP3 IR Magnets

Status of Magnet Production and Test Results

The most significant advancement has been the test of the third US-AUP full size magnet (MQXFA03). It reached nominal gradient with limited training and is the first magnet ready to be included in the first cold mass to be installed in the IT-String test.

WP3 IR Magnets

Status of MQXF production and test results

After the successful tests of MQXFA03 and MQXFA04, that allowed last year to obtain the approval of the US contribution by the DOE, MQXFA05 has been tested in May 2021.

WP3 IR Magnets