COVID-19 Impact on Schedule and Update on Civil Engineering Works
The COVID-19 restrictions have impacted the schedules of the LS2 and of the HL-LHC activities. Concerning the LS2 schedule, the hardware commissioning of LHC should be completed by March 2021 for all sectors except the S67.
COVID-19, CERN and HL-LHC
After having observed the first cases of illness in Italy and the following isolation measures, the coronavirus SARS-Cov-2, causing the severe respiratory illness COVID-19, became a subject of major concern in Europe during February 2020.
Update on the HL-LHC Project Status - Issue 4
The period following the 9th Collaboration Meeting in Fermilab, 14-17 November 2019, has been exceptionally rich in events. The most striking has certainly been the COVID-19 emergency, with long periods of lockdown almost everywhere.
Planning of the 2021 Annual Meeting
Due to the COVID-19 restrictions last year, the 2020 annual meeting initially planned to take place in Uppsala had to be postponed and instead the 10th HL-LHC Collaboration Meeting was held in virtual form and limited to plenary sessions.
HL-LHC Industrialization
The High-Luminosity Project is nowadays in the transition from the prototyping phase into full construction mode and most of the activities in view of the series production for the HL-LHC hardware have already started.
HL-LHC procurement and current market situation
The High-Luminosity Project is finalising the transition from the prototyping phase into full construction mode and most of the activities in view of the series production for the HL-LHC hardware have already started across all work-packages.