  • Cold Powering System transitions into preparation stages for installation following completion of collaboration deliverables

    Cold Powering System transitions into preparation stages for installation following completion of collaboration deliverables

    Following the steady progress of production of the Cold Powering Systems, including the completion of deliverables from SOTON and Uppsala University, preparations are well underway for installation in the underground.  Activities for the powering of the HiLumi magnets (Work Package 6A) in 2026 are focused on the assembly and testing of the series Cold Powering

    Explore →

  • Cold Powering System: confidence and validation for future installations, and series production progress

    Cold Powering System: confidence and validation for future installations, and series production progress

    The HL-LHC Cold Powering Systems transfer the current from the power converters, located in the new underground galleries, to the superconducting magnets of the HL-LHC Inner Triplets and Matching Sections, in the LHC tunnel, on either side of Point 1 and Point 5. Eight systems plus two spares of two different types, X for the

    Explore →

  • Progress with series production of DFHX/M by the University of Uppsala and DFX/M by the University of Southampton

    Progress with series production of DFHX/M by the University of Uppsala and DFX/M by the University of Southampton

    The HL-LHC cold powering systems transfer the current from the power converters, located in the new underground galleries, to the superconducting magnets of the HL-LHC inner triplets and matching sections at Point 1 and Point 5. Eight systems plus two spares of each of the two different types – ‘X’ for the inner triplets; ‘M’